New Britain 2024 Paving Program to Begin in June
1 min read

New Britain 2024 Paving Program to Begin in June

The New Britain Public Works Department is to carry out its 2024 road paving program, starting on June 17th.

The Department says that the program, “is expected to last approximately six to seven weeks.”

“For the majority of streets the rehabilitation work involves milling off the top 2” of existing pavement and then installing 2” of new pavement,” the Department says.

NameFromTo
Albany AvenueClinton StAlden St
Alexander RoadMiriam RdStanley St
Bank StreetMain StColumbus Blvd
Capitol AvenueBurritt Steast end
Davis StreetDoris StCarmody St
Dean DriveSlater RoadWalker Road
Doris StreetGold StGrove St
High StreetW Main StColumbus Blvd
High StreetMyrtle StBroad St
High StreetBroad StBiruta Street
Lorraine StreetLasalle StreetMilton Street
McClintock StreetLasalle StreetEddy Glover Blvd
Nash Streetwest endAlbany Av
Norton RoadW Main StSlater Rd
Overlook AvenueCorbin AvFarmington Av
Pentlow AvenueCorbin AvFarmington Av
Pulaski Streetwest endAlbany Av
Russwin RoadW Main StSlater Rd
Slater RoadW Main StClinton St
Stanley StreetKelsey StChestnut St
Torkom DriveSlater RdSlater Rd
Whiting StreetRRStanley St
Yeation StreetMalikowski CircleFarmington Avenue

“A total of $1,890,000 is appropriated for milling and paving this year with funding from state Road Aid, the Local Capital Improvement Program (LoCIP) and the city’s 1% for roads program,” said Council Majority Leader, Ald. John McNamara (D-4).

Public Works provides a web site for, “Paving Detailed Daily Updates,” which it says, “will begin approx. June 12.”