Allen St. Drainage Improvements and Reconstruction Phase 2 Project Update
To: Property Owners and Residents in the Allen St. Basin and in the Hampton-Eton Sub-Basin. The Allen, Brighton, Stewart, Hampton, Eton, Newbury, Roxbury Neighborhoods.
Mark Moriarty, Mark Czerepuszko, Jason Outlaw and Cardinal Engineers hosted an informational meeting Thursday 11-14-24. We were pleased with the presentation. The planning is moving along. The bid ready documents should be completed by 4-1-25 per Director Moriarty.
“The City of New Britain, alongside Cardinal Engineering, are working on the design of the Allen St. Drainage Improvements and Reconstruction Phase 2 Project. This project is the second phase of improvements to Allen St. which focuses on mitigating the reoccurring flooding in the area as well as completing the corridors’ streetscape improvements. This phase of the Allen St. Improvements involves approximately 0.7 miles of Allen St. from Oak St. to Beacon St.”
“Here are some of the improvements:
- New 54″ to 66″ reinforced concrete storm mains will be installed to replace the existing 24″clay storm main from Dixon to Beacon.
- New sidewalk and granite curbing will be installed from Oak to Stanley.
- From Oak to Stanley, the road will be reconstructed with new pavement.
- Existing asphalt will be milled and paved from Stanley to Beacon.
- 2500′ of existing 100 year old water main will be replaced.
- The sanitary sewer main will be upgraded from a 12″ clay pipe to a 24″ PVC pipe.
- Based on the preliminary estimate, the construction cost will be approximately $14.4M.”
It’s the City’s responsibility and policy to keep our property owners and residents informed and involved when such projects are undertaken. We certainly appreciate the extra efforts with this costly, complex and long overdue project. Now we need to fully fund the project and complete the construction in a timely manner for the benefit of all.
Our city officials (elected and appointed) are working to complete this project as soon as possible. Now our state legislative delegation (Lopes, B. Sanchez, M. Sanchez, Turco, Defronzo), bonding commission leaders Napoli and Piscopo, and Governor Lamont must close the deal regarding the state bonding initiative of $10M.
See flyer, below.
Mayor Stewart has already committed approximately $4.4M to the project. We applaud everybody’s efforts thus far. But there is more to do…
We will continue with our efforts to champion this project to completion for the benefit of our property owners and residents in the 177 acres of developed, congested, critical residential neighborhoods noted above. We cannot take our foot off the gas. The flooding must stop as soon as possible.
Thank you.
Sincerely,
F&S Chase
Recent frequent flooding photos:
Stanley-Roxbury-Newbury Typical Retention Pond Flooding.
Hampton-Eton Typical Flooding.
24 Roxbury Typical Flooding.
Newbury Typical Flooding.
Recent frequent flooding events:
- July 4 and 16, 2023
- August 18, 2023
- September 9 and September 13, 2023
- December 18, 2023
- June 22 and June 30, 2024
- August 18 and August 19, 2024
Our interview with NBC-WVIT:
Residents of New Britain neighbors blame city for flooding issues